Frito Lay Distribution Center
Frito-Lay has a large distribution center in West Valley City, Utah that required several improvements and expansions. FOCUS construction staking crews laid out the site’s expansions which included new building corners, bolt patterns, storage silos, and a parking lot.
The site's concrete had not yet cured when the field crew arrived to stake out the bolt patterns. As uncured concrete can change the locations of the bolts, FOCUS was tasked with monitoring the concrete for possible changes. The FOCUS crew set up an exterior control using a Tribrach and prism that could be rotated to verify that tolerances were being maintained.
Client | Haskell Construction |
Location | West Valley, Utah |
Project Duration | February 2018 - August 2018 |
Services | Construction Staking |